Accelerating Infrastructure Development: A Case Study of the Quebrada 4 Bridge Using Innovative Construction Techniques in Peru

This study explores the expedited construction of the Quebrada 4 Bridge on the Casas Quemadas Highway in Lancones, Piura, Peru. Completed in March 2023, this bridge is pivotal for connecting local towns to the Ecuadorian border and enhancing agricultural, livestock, and tourism sectors. Utilizing a...

Descripción completa

Guardado en:
Detalles Bibliográficos
Autores principales: Sergio Nehemías Llanos Diaz, Gerber Zavala Ascaño, Edward Paúl Espinoza Mejía
Formato: Capítulo de libro
Lenguaje:inglés
Publicado: 2026
Materias:
Acceso en línea:Enlace permanente (DOI o Handle)
Etiquetas: Agregar Etiqueta
Sin Etiquetas, Sea el primero en etiquetar este registro!
_version_ 1881700512091340800
author Sergio Nehemías Llanos Diaz
Gerber Zavala Ascaño
Edward Paúl Espinoza Mejía
author_browse Edward Paúl Espinoza Mejía
Gerber Zavala Ascaño
Sergio Nehemías Llanos Diaz
author_facet Sergio Nehemías Llanos Diaz
Gerber Zavala Ascaño
Edward Paúl Espinoza Mejía
author_sort Sergio Nehemías Llanos Diaz
collection Producción científica
description This study explores the expedited construction of the Quebrada 4 Bridge on the Casas Quemadas Highway in Lancones, Piura, Peru. Completed in March 2023, this bridge is pivotal for connecting local towns to the Ecuadorian border and enhancing agricultural, livestock, and tourism sectors. Utilizing a novel battery bridge design and arch structures featuring SP MP152 multiplate galvanized corrugated sheets, this project introduced innovative engineering approaches that substantially reduced costs and construction times relative to traditional reinforced concrete bridges. Notable achievements include a reduction in material costs, a decrease in installation time, and streamlined design processes. Furthermore, the bridge's enhanced hydraulic capacity is crucial in mitigating the effects of recurring El Niño events, ensuring its operational integrity amid fluctuating weather conditions and growing commercial demands. The rapid construction timeline, culminating in broad local community support, encompassed foundational work completed in just four days, with subsequent phases of slab assembly, backfill, and head construction executed over 14 days. Integrating Building Information Modeling (BIM) and photogrammetry was crucial in aligning digital planning with physical topography, averting potential compatibility issues. Even under adverse conditions, such as those presented by Cyclone Yaku, the structure demonstrated remarkable resilience, maintaining essential connectivity. This research underscores the potential of advanced design and construction methodologies to accelerate infrastructure development, bolster socioeconomic growth, and enhance environmental resilience.
format Book chapter
id openalex:W7167887723
institution UPeU
language English
publishDate 2026
publishDateRange 2026
publishDateSort 2026
record_format dspace
spelling openalex:W7167887723Accelerating Infrastructure Development: A Case Study of the Quebrada 4 Bridge Using Innovative Construction Techniques in PeruSergio Nehemías Llanos DiazGerber Zavala AscañoEdward Paúl Espinoza Mejíaarch bridgesaccelerated bridge constructionEl Niñobuilding information modelingphotogrammetrybridge resilienceinfrastructure developmentPiuraCivil and Structural Engineering ResearchStructural Engineering and Materials AnalysisBIM and Construction IntegrationThis study explores the expedited construction of the Quebrada 4 Bridge on the Casas Quemadas Highway in Lancones, Piura, Peru. Completed in March 2023, this bridge is pivotal for connecting local towns to the Ecuadorian border and enhancing agricultural, livestock, and tourism sectors. Utilizing a novel battery bridge design and arch structures featuring SP MP152 multiplate galvanized corrugated sheets, this project introduced innovative engineering approaches that substantially reduced costs and construction times relative to traditional reinforced concrete bridges. Notable achievements include a reduction in material costs, a decrease in installation time, and streamlined design processes. Furthermore, the bridge's enhanced hydraulic capacity is crucial in mitigating the effects of recurring El Niño events, ensuring its operational integrity amid fluctuating weather conditions and growing commercial demands. The rapid construction timeline, culminating in broad local community support, encompassed foundational work completed in just four days, with subsequent phases of slab assembly, backfill, and head construction executed over 14 days. Integrating Building Information Modeling (BIM) and photogrammetry was crucial in aligning digital planning with physical topography, averting potential compatibility issues. Even under adverse conditions, such as those presented by Cyclone Yaku, the structure demonstrated remarkable resilience, maintaining essential connectivity. This research underscores the potential of advanced design and construction methodologies to accelerate infrastructure development, bolster socioeconomic growth, and enhance environmental resilience.Book chapterhttps://doi.org/10.1520/stp165820240063W7167887723en2026-07-01
spellingShingle arch bridges
accelerated bridge construction
El Niño
building information modeling
photogrammetry
bridge resilience
infrastructure development
Piura
Civil and Structural Engineering Research
Structural Engineering and Materials Analysis
BIM and Construction Integration
Sergio Nehemías Llanos Diaz
Gerber Zavala Ascaño
Edward Paúl Espinoza Mejía
Accelerating Infrastructure Development: A Case Study of the Quebrada 4 Bridge Using Innovative Construction Techniques in Peru
title Accelerating Infrastructure Development: A Case Study of the Quebrada 4 Bridge Using Innovative Construction Techniques in Peru
title_full Accelerating Infrastructure Development: A Case Study of the Quebrada 4 Bridge Using Innovative Construction Techniques in Peru
title_fullStr Accelerating Infrastructure Development: A Case Study of the Quebrada 4 Bridge Using Innovative Construction Techniques in Peru
title_full_unstemmed Accelerating Infrastructure Development: A Case Study of the Quebrada 4 Bridge Using Innovative Construction Techniques in Peru
title_short Accelerating Infrastructure Development: A Case Study of the Quebrada 4 Bridge Using Innovative Construction Techniques in Peru
title_sort accelerating infrastructure development a case study of the quebrada 4 bridge using innovative construction techniques in peru
topic arch bridges
accelerated bridge construction
El Niño
building information modeling
photogrammetry
bridge resilience
infrastructure development
Piura
Civil and Structural Engineering Research
Structural Engineering and Materials Analysis
BIM and Construction Integration
topic_facet arch bridges
accelerated bridge construction
El Niño
building information modeling
photogrammetry
bridge resilience
infrastructure development
Piura
Civil and Structural Engineering Research
Structural Engineering and Materials Analysis
BIM and Construction Integration
url https://doi.org/10.1520/stp165820240063
work_keys_str_mv AT sergionehemiasllanosdiaz acceleratinginfrastructuredevelopmentacasestudyofthequebrada4bridgeusinginnovativeconstructiontechniquesinperu
AT gerberzavalaascano acceleratinginfrastructuredevelopmentacasestudyofthequebrada4bridgeusinginnovativeconstructiontechniquesinperu
AT edwardpaulespinozamejia acceleratinginfrastructuredevelopmentacasestudyofthequebrada4bridgeusinginnovativeconstructiontechniquesinperu